when we use MRP Type code of G with a cover time of 5 days on a Manufactured part, it does not combine the requisitions into a single requisition. Has anyone successfully used G codes on Manufactured parts
Best answer by Richard Owen
View originalwhen we use MRP Type code of G with a cover time of 5 days on a Manufactured part, it does not combine the requisitions into a single requisition. Has anyone successfully used G codes on Manufactured parts
Best answer by Richard Owen
View originalHi,
Is the part being planned by MRP? Note that the functionality does not work with MS Level 1 parts.
Also, have you checked the Min, Max and Multiple Lot Size values on the Mfg Part?
The part is checked to be planned by MRP That would explain it.